Milestone Map: QuoteNo: Q12171 / ProdNo: 1110936


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 4/11/2025 4/11/2025 Eng Kick Off
Financial Review 4/18/2025 Financial Review
Initial Design Review 4/30/2025 8/29/2025 Initial Design Review Scott Tidwell
Long Lead Release 4/10/2025 Long Lead Release Date
Drawing Package Submittal 5/6/2025 Drawing Package Submittal Date
Drawing Package Approval 6/10/2025 Drawing Package Approval Date
Full BOM Release 4/10/2025 Full BOM Release Date
Final Design Review 5/9/2025 5/9/2025 Final Design Review Joe Marshall
Design Completion Date 5/12/2025 Design Completion Date
Shop Release 6/13/2025 8/29/2025 Shop Release Scott Tidwell
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned