Milestone Map: QuoteNo: 12004 / ProdNo: 1110869


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 3/25/2025 3/25/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 3/26/2025 3/25/2025 Final Quote Review Joe Marshall
Contract Review 3/25/2025 Contract Review Joe Marshall
Order Entry 3/25/2025 3/25/2025 Order Entry Joe Marshall
Eng KickOff 3/28/2025 3/28/2025 Eng Kick Off Dylan Smith
Financial Review 3/28/2025 3/28/2025 Financial Review
Initial Design Review Initial Design Review
Long Lead Release 3/28/2025 3/28/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 4/2/2025 4/2/2025 Full BOM Release Date
Final Design Review 4/4/2025 7/31/2025 Final Design Review Dylan Smith
Design Completion Date 4/2/2025 4/2/2025 Design Completion Date
Shop Release 8/4/2025 7/23/2025 Shop Release Dylan Smith
Production Complete 8/27/2025 Production Complete
Order Close Out 8/29/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 9/1/2025 9/26/2025 Project Wrap Up
Lessons Learned Lessons Learned