Milestone Map: QuoteNo: Q12245 / ProdNo: 1110679


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 2/10/2025 2/10/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 2/11/2025 2/12/2025 Final Quote Review Joe Marshall
Contract Review 3/21/2025 Contract Review Joe Marshall
Order Entry 3/21/2025 3/21/2025 Order Entry Joe Marshall
Eng KickOff 3/25/2025 3/25/2025 Eng Kick Off Dylan Smith
Financial Review 3/21/2025 3/21/2025 Financial Review
Initial Design Review Initial Design Review
Long Lead Release 3/21/2025 3/21/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 3/26/2025 3/26/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 3/26/2025 3/26/2025 Design Completion Date
Shop Release 5/19/2025 4/29/2025 Shop Release
Production Complete 5/30/2025 5/16/2025 Production Complete
Order Close Out 6/3/2025 Order Close Out
Project Wrap Up 6/18/2025 11/4/2025 Project Wrap Up Dylan Smith
Lessons Learned Lessons Learned