Milestone Map: QuoteNo: 11999 / ProdNo: 1110668
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
1/29/2025
1/29/2025
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
2/3/2025
2/3/2025
Final Quote Review
Joe Marshall
Contract Review
3/20/2025
Contract Review
Joe Marshall
Order Entry
3/20/2025
3/20/2025
Order Entry
Joe Marshall
Eng KickOff
3/25/2025
3/25/2025
Eng Kick Off
Dylan Smith
Financial Review
Financial Review
Initial Design Review
3/31/2025
3/31/2025
Initial Design Review
Dylan Smith
Long Lead Release
3/21/2025
3/21/2025
Long Lead Release Date
Drawing Package Submittal
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
3/21/2025
3/21/2025
Full BOM Release Date
Final Design Review
Final Design Review
Design Completion Date
3/21/2025
3/21/2025
Design Completion Date
Shop Release
5/12/2025
4/28/2025
Shop Release
Production Complete
5/22/2025
Production Complete
Order Close Out
5/26/2025
Order Close Out
Project Wrap Up
6/6/2025
Project Wrap Up
Lessons Learned
Lessons Learned