Milestone Map: QuoteNo: 11999 / ProdNo: 1110668


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 1/29/2025 1/29/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 2/3/2025 2/3/2025 Final Quote Review Joe Marshall
Contract Review 3/20/2025 Contract Review Joe Marshall
Order Entry 3/20/2025 3/20/2025 Order Entry Joe Marshall
Eng KickOff 3/25/2025 3/25/2025 Eng Kick Off Dylan Smith
Financial Review Financial Review
Initial Design Review 3/31/2025 3/31/2025 Initial Design Review Dylan Smith
Long Lead Release 3/21/2025 3/21/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 3/21/2025 3/21/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 3/21/2025 3/21/2025 Design Completion Date
Shop Release 5/12/2025 4/28/2025 Shop Release
Production Complete 5/22/2025 Production Complete
Order Close Out 5/26/2025 Order Close Out
Project Wrap Up 6/6/2025 Project Wrap Up
Lessons Learned Lessons Learned