Milestone Map: QuoteNo: Q12154 / ProdNo: 1110666


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 11/15/2024 11/19/2024 Initial Quote Receipt & Review
Final Quote Review 12/2/2024 1/24/2025 Final Quote Review Joe Marshall
Contract Review 3/21/2025 Contract Review Darren Zielke
Order Entry 3/21/2025 3/21/2025 Order Entry Darren Zielke
Eng KickOff 3/26/2025 3/26/2025 Eng Kick Off Darren Zielke
Financial Review 4/15/2025 4/3/2025 Financial Review Darren Zielke
Initial Design Review 4/15/2025 4/16/2025 Initial Design Review Darren Zielke
Long Lead Release 3/31/2025 3/31/2025 Long Lead Release Date
Drawing Package Submittal 4/16/2025 5/28/2025 Drawing Package Submittal Date
Drawing Package Approval 4/21/2025 6/20/2025 Drawing Package Approval Date
Full BOM Release 4/23/2025 6/26/2025 Full BOM Release Date
Final Design Review 4/21/2025 6/13/2025 Final Design Review Darren Zielke
Design Completion Date 4/22/2025 6/26/2025 Design Completion Date
Shop Release 5/12/2025 7/11/2025 Shop Release Darren Zielke
Production Complete 5/9/2025 9/2/2025 Production Complete
Order Close Out 6/2/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 6/13/2025 9/25/2025 Project Wrap Up
Lessons Learned Lessons Learned