Milestone Map: QuoteNo: Q12117 / ProdNo: 1110613


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 1/24/2025 1/28/2025 Initial Quote Receipt & Review Darren Zielke
Final Quote Review 2/3/2025 2/4/2025 Final Quote Review Darren Zielke
Contract Review 3/17/2025 Contract Review Darren Zielke
Order Entry 3/17/2025 3/18/2025 Order Entry Darren Zielke
Eng KickOff 4/2/2025 4/2/2025 Eng Kick Off Darren Zielke
Financial Review 4/15/2025 4/25/2025 Financial Review Darren Zielke
Initial Design Review 4/18/2025 4/16/2025 Initial Design Review Darren Zielke
Long Lead Release 4/8/2025 4/8/2025 Long Lead Release Date
Drawing Package Submittal 4/14/2025 4/9/2025 Drawing Package Submittal Date
Drawing Package Approval 4/25/2025 4/10/2025 Drawing Package Approval Date
Full BOM Release 5/30/2025 6/13/2025 Full BOM Release Date
Final Design Review 4/15/2025 6/13/2025 Final Design Review Darren Zielke
Design Completion Date 5/30/2025 6/13/2025 Design Completion Date
Shop Release 9/5/2025 7/11/2025 Shop Release Darren Zielke
Production Complete 11/3/2025 9/5/2025 Production Complete
Order Close Out 11/4/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 11/14/2025 Project Wrap Up
Lessons Learned Lessons Learned