Milestone Map: QuoteNo: Q12117 / ProdNo: 1110613
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
1/24/2025
1/28/2025
Initial Quote Receipt & Review
Darren Zielke
Final Quote Review
2/3/2025
2/4/2025
Final Quote Review
Darren Zielke
Contract Review
3/17/2025
Contract Review
Darren Zielke
Order Entry
3/17/2025
3/18/2025
Order Entry
Darren Zielke
Eng KickOff
4/2/2025
4/2/2025
Eng Kick Off
Darren Zielke
Financial Review
4/15/2025
4/25/2025
Financial Review
Darren Zielke
Initial Design Review
4/18/2025
4/16/2025
Initial Design Review
Darren Zielke
Long Lead Release
4/8/2025
4/8/2025
Long Lead Release Date
Drawing Package Submittal
4/14/2025
4/9/2025
Drawing Package Submittal Date
Drawing Package Approval
4/25/2025
4/10/2025
Drawing Package Approval Date
Full BOM Release
5/30/2025
6/13/2025
Full BOM Release Date
Final Design Review
4/15/2025
6/13/2025
Final Design Review
Darren Zielke
Design Completion Date
5/30/2025
6/13/2025
Design Completion Date
Shop Release
9/5/2025
7/11/2025
Shop Release
Darren Zielke
Production Complete
11/3/2025
9/5/2025
Production Complete
Order Close Out
11/4/2025
9/24/2025
Order Close Out
Noelle Sorano
Project Wrap Up
11/14/2025
Project Wrap Up
Lessons Learned
Lessons Learned