Milestone Map: QuoteNo: Q12201 / ProdNo: 1109452


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 2/5/2025 2/5/2025 Eng Kick Off
Financial Review 4/4/2025 4/4/2025 Financial Review
Initial Design Review 10/23/2025 Initial Design Review Paul Brown
Long Lead Release 4/1/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 5/28/2025 Full BOM Release Date
Final Design Review 3/10/2025 2/7/2025 Final Design Review
Design Completion Date 5/28/2025 Design Completion Date
Shop Release 3/10/2025 3/10/2025 Shop Release Joe Marshall
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned