Milestone Map: QuoteNo: 11993 / ProdNo: 1109202


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 12/13/2024 12/13/2024 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 12/19/2024 1/23/2025 Final Quote Review Joe Marshall
Contract Review 1/22/2025 Contract Review Joe Marshall
Order Entry 1/22/2025 1/22/2025 Order Entry Joe Marshall
Eng KickOff 1/29/2025 1/29/2025 Eng Kick Off Kyle Swindlehurst
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release 1/28/2025 1/28/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 2/14/2025 9/5/2025 Full BOM Release Date
Final Design Review 9/26/2025 Final Design Review Kyle Swindlehurst
Design Completion Date 2/14/2025 9/17/2025 Design Completion Date
Shop Release 11/5/2025 10/23/2025 Shop Release Kyle Swindlehurst
Production Complete 1/22/2026 Production Complete
Order Close Out 1/27/2026 Order Close Out
Project Wrap Up 2/6/2026 Project Wrap Up
Lessons Learned Lessons Learned