Milestone Map: QuoteNo: Q12012 / ProdNo: 1108914


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 1/20/2025 1/15/2025 Eng Kick Off
Financial Review Financial Review
Initial Design Review 2/7/2025 2/7/2025 Initial Design Review
Long Lead Release 1/15/2025 Long Lead Release Date
Drawing Package Submittal 3/4/2025 Drawing Package Submittal Date
Drawing Package Approval 3/10/2025 Drawing Package Approval Date
Full BOM Release 3/10/2025 Full BOM Release Date
Final Design Review 2/14/2025 3/17/2025 Final Design Review
Design Completion Date 5/30/2025 Design Completion Date
Shop Release 7/25/2025 5/30/2025 Shop Release Scott Tidwell
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned