Milestone Map: QuoteNo: Q11932 / ProdNo: 1108865


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 4/26/2024 4/26/2024 Initial Quote Receipt & Review
Final Quote Review 5/23/2024 5/7/2024 Final Quote Review Darren Zielke
Contract Review 1/10/2025 Contract Review Darren Zielke
Order Entry 1/10/2025 1/10/2025 Order Entry Darren Zielke
Eng KickOff 1/15/2025 1/15/2025 Eng Kick Off Darren Zielke
Financial Review 8/19/2025 9/5/2025 Financial Review Frank Edwards
Initial Design Review 2/20/2025 8/21/2025 Initial Design Review Darren Zielke
Long Lead Release Long Lead Release Date
Drawing Package Submittal 2/20/2025 7/7/2025 Drawing Package Submittal Date
Drawing Package Approval 3/7/2025 9/2/2025 Drawing Package Approval Date
Full BOM Release 8/1/2025 Full BOM Release Date
Final Design Review 9/19/2025 Final Design Review
Design Completion Date 9/19/2025 Design Completion Date
Shop Release 9/19/2025 Shop Release
Production Complete 11/3/2025 Production Complete
Order Close Out 11/21/2025 Order Close Out
Project Wrap Up 11/26/2025 Project Wrap Up
Lessons Learned Lessons Learned