Milestone Map: QuoteNo: Q12140 / ProdNo: 1108072


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 1/27/2025 1/24/2025 Eng Kick Off
Financial Review Financial Review
Initial Design Review 1/31/2025 1/28/2025 Initial Design Review
Long Lead Release 1/24/2025 Long Lead Release Date
Drawing Package Submittal 1/28/2025 Drawing Package Submittal Date
Drawing Package Approval 4/29/2025 Drawing Package Approval Date
Full BOM Release 2/3/2025 Full BOM Release Date
Final Design Review 1/31/2025 1/28/2025 Final Design Review
Design Completion Date 3/24/2025 Design Completion Date
Shop Release 2/28/2025 3/24/2025 Shop Release
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up