Milestone Map: QuoteNo: Q12071 / ProdNo: 1107468
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
Initial Quote Receipt & Review
Final Quote Review
Final Quote Review
Contract Review
Contract Review
Order Entry
Order Entry
Eng KickOff
11/4/2024
11/4/2024
Eng Kick Off
Financial Review
12/2/2024
12/2/2024
Financial Review
Initial Design Review
3/3/2025
3/3/2025
Initial Design Review
Paul Brown
Long Lead Release
11/26/2024
Long Lead Release Date
Drawing Package Submittal
1/9/2025
Drawing Package Submittal Date
Drawing Package Approval
3/18/2025
Drawing Package Approval Date
Full BOM Release
3/12/2025
Full BOM Release Date
Final Design Review
3/3/2025
3/11/2025
Final Design Review
Design Completion Date
4/18/2025
Design Completion Date
Shop Release
4/15/2025
4/25/2025
Shop Release
Production Complete
Production Complete
Order Close Out
Order Close Out
Project Wrap Up
Project Wrap Up
Lessons Learned
Lessons Learned