Milestone Map: QuoteNo: Q12071 / ProdNo: 1107468


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 11/4/2024 11/4/2024 Eng Kick Off
Financial Review 12/2/2024 12/2/2024 Financial Review
Initial Design Review 3/3/2025 3/3/2025 Initial Design Review Paul Brown
Long Lead Release 11/26/2024 Long Lead Release Date
Drawing Package Submittal 1/9/2025 Drawing Package Submittal Date
Drawing Package Approval 3/18/2025 Drawing Package Approval Date
Full BOM Release 3/12/2025 Full BOM Release Date
Final Design Review 3/3/2025 3/11/2025 Final Design Review
Design Completion Date 4/18/2025 Design Completion Date
Shop Release 4/15/2025 4/25/2025 Shop Release
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned