Milestone Map: QuoteNo: Q11782 / ProdNo: 1106929


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 10/9/2024 8/29/2025 Eng Kick Off Scott Tidwell
Financial Review Financial Review
Initial Design Review 11/27/2024 8/29/2025 Initial Design Review Scott Tidwell
Long Lead Release 11/21/2024 Long Lead Release Date
Drawing Package Submittal 12/19/2024 Drawing Package Submittal Date
Drawing Package Approval 12/19/2024 Drawing Package Approval Date
Full BOM Release 1/6/2025 Full BOM Release Date
Final Design Review 11/27/2024 2/5/2025 Final Design Review
Design Completion Date 1/6/2025 Design Completion Date
Shop Release 4/1/2025 9/16/2025 Shop Release Scott Tidwell
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned