Milestone Map: QuoteNo: 11890 / ProdNo: 1103385
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
3/5/2024
3/6/2024
Initial Quote Receipt & Review
Darren Zielke
Final Quote Review
3/8/2024
3/18/2024
Final Quote Review
Darren Zielke
Contract Review
4/4/2024
Contract Review
Darren Zielke
Order Entry
4/4/2024
4/4/2024
Order Entry
Darren Zielke
Eng KickOff
4/26/2024
5/21/2024
Eng Kick Off
Darren Zielke
Financial Review
8/23/2024
6/10/2024
Financial Review
Darren Zielke
Initial Design Review
7/26/2024
6/10/2024
Initial Design Review
Darren Zielke
Long Lead Release
7/18/2024
6/17/2024
Long Lead Release Date
Drawing Package Submittal
7/26/2024
6/13/2024
Drawing Package Submittal Date
Drawing Package Approval
7/30/2024
7/4/2024
Drawing Package Approval Date
Full BOM Release
9/10/2024
1/6/2025
Full BOM Release Date
Final Design Review
8/23/2024
1/2/2025
Final Design Review
Design Completion Date
9/10/2024
1/6/2025
Design Completion Date
Shop Release
11/1/2024
1/6/2025
Shop Release
Production Complete
1/30/2025
4/7/2025
Production Complete
Order Close Out
2/3/2025
Order Close Out
Project Wrap Up
2/14/2025
Project Wrap Up
Lessons Learned
Lessons Learned