Milestone Map: QuoteNo: Q12365 / ProdNo: 1112391


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 5/13/2025 5/12/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 5/16/2025 5/13/2025 Final Quote Review Joe Marshall
Contract Review 5/30/2025 Contract Review Joe Marshall
Order Entry 5/23/2025 5/30/2025 Order Entry Joe Marshall
Eng KickOff 6/4/2025 6/10/2025 Eng Kick Off Dylan Smith
Financial Review 6/13/2025 8/6/2025 Financial Review Dylan Smith
Initial Design Review 6/13/2025 6/13/2025 Initial Design Review Dylan Smith
Long Lead Release 6/4/2025 6/10/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 6/4/2025 7/16/2025 Full BOM Release Date
Final Design Review 6/26/2025 6/25/2025 Final Design Review Dylan Smith
Design Completion Date 6/16/2025 8/6/2025 Design Completion Date
Shop Release 6/16/2025 7/17/2025 Shop Release Dylan Smith
Production Complete 7/17/2025 7/23/2025 Production Complete
Order Close Out 7/21/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 7/25/2025 9/26/2025 Project Wrap Up
Lessons Learned Lessons Learned