Milestone Map: QuoteNo: Q12347 / ProdNo: 1112114


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 4/29/2025 4/29/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 5/1/2025 4/29/2025 Final Quote Review Joe Marshall
Contract Review 5/15/2025 Contract Review Joe Marshall
Order Entry 5/15/2025 5/15/2025 Order Entry Joe Marshall
Eng KickOff 5/19/2025 5/19/2025 Eng Kick Off
Financial Review 5/20/2025 5/20/2025 Financial Review
Initial Design Review Initial Design Review
Long Lead Release 5/20/2025 5/19/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 5/20/2025 5/19/2025 Full BOM Release Date
Final Design Review 5/30/2025 5/28/2025 Final Design Review Dylan Smith
Design Completion Date 5/30/2025 5/19/2025 Design Completion Date
Shop Release 6/2/2025 6/11/2025 Shop Release Dylan Smith
Production Complete 6/19/2025 Production Complete
Order Close Out 6/23/2025 8/28/2025 Order Close Out Dylan Smith
Project Wrap Up 7/2/2025 9/26/2025 Project Wrap Up
Lessons Learned Lessons Learned