Milestone Map: QuoteNo: Q12323 / ProdNo: 1112394


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 4/4/2025 7/22/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 4/7/2025 7/22/2025 Final Quote Review Joe Marshall
Contract Review 5/23/2025 7/22/2025 Contract Review Joe Marshall
Order Entry 5/23/2025 7/22/2025 Order Entry Joe Marshall
Eng KickOff 5/30/2025 7/23/2025 Eng Kick Off Frank Edwards
Financial Review 6/13/2025 7/23/2025 Financial Review Frank Edwards
Initial Design Review 7/23/2025 Initial Design Review Frank Edwards
Long Lead Release 5/30/2025 5/30/2025 Long Lead Release Date
Drawing Package Submittal 6/13/2025 6/9/2025 Drawing Package Submittal Date
Drawing Package Approval 6/18/2025 6/11/2025 Drawing Package Approval Date
Full BOM Release 6/6/2025 6/6/2025 Full BOM Release Date
Final Design Review 6/13/2025 7/23/2025 Final Design Review Frank Edwards
Design Completion Date 6/18/2025 6/18/2025 Design Completion Date
Shop Release 8/11/2025 7/23/2025 Shop Release Dylan Smith
Production Complete 8/22/2025 10/8/2025 Production Complete
Order Close Out 8/26/2025 Order Close Out
Project Wrap Up 8/29/2025 10/9/2025 Project Wrap Up
Lessons Learned Lessons Learned