Milestone Map: QuoteNo: Q12189 / ProdNo: 1115755
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
1/3/2025
10/17/2025
Initial Quote Receipt & Review
Frank Edwards
Final Quote Review
1/10/2025
10/17/2025
Final Quote Review
Frank Edwards
Contract Review
10/17/2025
Contract Review
Frank Edwards
Order Entry
10/17/2025
10/30/2025
Order Entry
Frank Edwards
Eng KickOff
10/22/2025
10/23/2025
Eng Kick Off
Kyle Swindlehurst
Financial Review
10/29/2025
10/23/2025
Financial Review
Kyle Swindlehurst
Initial Design Review
10/30/2025
10/30/2025
Initial Design Review
Frank Edwards
Long Lead Release
11/5/2025
Long Lead Release Date
Drawing Package Submittal
11/21/2025
Drawing Package Submittal Date
Drawing Package Approval
12/5/2025
Drawing Package Approval Date
Full BOM Release
12/10/2025
Full BOM Release Date
Final Design Review
12/12/2025
Final Design Review
Design Completion Date
12/19/2025
Design Completion Date
Shop Release
2/16/2026
Shop Release
Production Complete
3/26/2026
Production Complete
Order Close Out
3/31/2026
Order Close Out
Project Wrap Up
4/3/2026
Project Wrap Up
Lessons Learned
4/8/2026
Lessons Learned