Milestone Map: QuoteNo: Q12133 / ProdNo: 1114523


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 11/7/2024 11/7/2024 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 11/11/2024 4/29/2025 Final Quote Review Joe Marshall
Contract Review 8/22/2025 Contract Review Joe Marshall
Order Entry 8/6/2025 8/22/2025 Order Entry Frank Edwards
Eng KickOff 8/27/2025 8/26/2025 Eng Kick Off Anthony Bizon
Financial Review 10/2/2025 9/17/2025 Financial Review Frank Edwards
Initial Design Review 9/29/2025 Initial Design Review Frank Edwards
Long Lead Release 8/22/2025 8/22/2025 Long Lead Release Date
Drawing Package Submittal 9/10/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/29/2025 9/11/2025 Full BOM Release Date
Final Design Review 10/2/2025 10/2/2025 Final Design Review Frank Edwards
Design Completion Date 9/5/2025 9/11/2025 Design Completion Date
Shop Release 9/15/2025 9/12/2025 Shop Release Anthony Bizon
Production Complete 10/16/2025 Production Complete
Order Close Out 10/20/2025 Order Close Out
Project Wrap Up 10/24/2025 Project Wrap Up
Lessons Learned Lessons Learned