Milestone Map: QuoteNo: Q12124 / ProdNo: 1112992
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
10/28/2024
10/28/2024
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
10/31/2024
11/6/2024
Final Quote Review
Joe Marshall
Contract Review
6/26/2025
6/26/2025
Contract Review
Joe Marshall
Order Entry
6/27/2025
7/25/2025
Order Entry
Joe Marshall
Eng KickOff
7/2/2025
7/7/2025
Eng Kick Off
Dylan Smith
Financial Review
8/1/2025
7/31/2025
Financial Review
Dylan Smith
Initial Design Review
Initial Design Review
Long Lead Release
7/3/2025
6/27/2025
Long Lead Release Date
Drawing Package Submittal
7/25/2025
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
7/11/2025
6/27/2025
Full BOM Release Date
Final Design Review
8/1/2025
8/1/2025
Final Design Review
Dylan Smith
Design Completion Date
8/1/2025
6/27/2025
Design Completion Date
Shop Release
11/3/2025
8/12/2025
Shop Release
Dylan Smith
Production Complete
11/21/2025
Production Complete
Order Close Out
11/26/2025
Order Close Out
Project Wrap Up
12/5/2025
Project Wrap Up
Lessons Learned
12/12/2025
Lessons Learned