Milestone Map: QuoteNo: Q12507 / ProdNo: 1116143
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
8/21/2025
10/31/2025
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
8/26/2025
10/31/2025
Final Quote Review
Joe Marshall
Contract Review
10/31/2025
Contract Review
Joe Marshall
Order Entry
10/31/2025
10/31/2025
Order Entry
Joe Marshall
Eng KickOff
11/4/2025
11/6/2025
Eng Kick Off
Scott Tidwell
Financial Review
11/6/2025
Financial Review
Scott Tidwell
Initial Design Review
11/6/2025
Initial Design Review
Scott Tidwell
Long Lead Release
11/4/2025
11/3/2025
Long Lead Release Date
Drawing Package Submittal
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
11/7/2025
11/6/2025
Full BOM Release Date
Final Design Review
Final Design Review
Design Completion Date
11/7/2025
Design Completion Date
Shop Release
1/6/2026
Shop Release
Production Complete
1/27/2026
Production Complete
Order Close Out
1/29/2026
Order Close Out
Project Wrap Up
2/13/2026
Project Wrap Up
Lessons Learned
Lessons Learned