Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 9/11/2025 10/30/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 9/24/2025 10/30/2025 Final Quote Review Frank Edwards
Contract Review 10/30/2025 10/30/2025 Contract Review Frank Edwards
Order Entry 10/31/2025 10/30/2025 Order Entry Frank Edwards
Eng KickOff 11/3/2025 11/3/2025 Eng Kick Off Phil Kimberlin
Financial Review Financial Review
Initial Design Review 11/11/2025 Initial Design Review Phil Kimberlin
Long Lead Release Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 10/30/2025 10/30/2025 Full BOM Release Date
Final Design Review 11/11/2025 Final Design Review Phil Kimberlin
Design Completion Date 11/14/2025 11/5/2025 Design Completion Date
Shop Release 1/5/2026 Shop Release
Production Complete 1/12/2026 Production Complete
Order Close Out 1/19/2026 Order Close Out
Project Wrap Up 1/23/2026 Project Wrap Up