Milestone Map: QuoteNo: Q12625 / ProdNo:


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 11/7/2025 10/30/2025 Initial Quote Receipt & Review Derrick Herr
Final Quote Review 11/6/2025 11/10/2025 Final Quote Review Derrick Herr
Contract Review 11/13/2025 Contract Review Frank Edwards
Order Entry 11/14/2025 11/14/2025 Order Entry Frank Edwards
Eng KickOff 11/17/2025 Eng Kick Off
Financial Review 12/2/2025 Financial Review
Initial Design Review Initial Design Review
Long Lead Release 11/19/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 12/3/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 12/5/2025 Design Completion Date
Shop Release 2/2/2026 Shop Release
Production Complete 3/9/2026 Production Complete
Order Close Out 3/19/2026 Order Close Out
Project Wrap Up 3/27/2026 Project Wrap Up
Lessons Learned Lessons Learned