Milestone Map: QuoteNo: Q12617 / ProdNo: 1116038
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
10/23/2025
10/23/2025
Initial Quote Receipt & Review
Derrick Herr
Final Quote Review
10/23/2025
10/24/2025
Final Quote Review
Frank Edwards
Contract Review
10/30/2025
Contract Review
Frank Edwards
Order Entry
10/30/2025
10/30/2025
Order Entry
Frank Edwards
Eng KickOff
10/31/2025
11/7/2025
Eng Kick Off
Darren Zielke
Financial Review
Financial Review
Initial Design Review
Initial Design Review
Long Lead Release
Long Lead Release Date
Drawing Package Submittal
11/7/2025
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
10/30/2025
10/30/2025
Full BOM Release Date
Final Design Review
11/7/2025
11/7/2025
Final Design Review
Darren Zielke
Design Completion Date
11/7/2025
11/7/2025
Design Completion Date
Shop Release
11/10/2025
11/7/2025
Shop Release
Darren Zielke
Production Complete
11/14/2025
Production Complete
Order Close Out
11/18/2025
Order Close Out
Project Wrap Up
11/20/2025
Project Wrap Up
Lessons Learned
11/21/2025
Lessons Learned