Milestone Map: QuoteNo: Q12334 / ProdNo: 1115658


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/26/2025 10/21/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 8/26/2025 10/21/2025 Final Quote Review Frank Edwards
Contract Review 10/14/2025 10/21/2025 Contract Review Frank Edwards
Order Entry 10/15/2025 10/21/2025 Order Entry Frank Edwards
Eng KickOff 10/27/2025 10/30/2025 Eng Kick Off Anthony Bizon
Financial Review 11/11/2025 11/12/2025 Financial Review Frank Edwards
Initial Design Review Initial Design Review
Long Lead Release Long Lead Release Date
Drawing Package Submittal 11/11/2025 11/3/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 11/11/2025 11/3/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 11/21/2025 11/3/2025 Design Completion Date
Shop Release 9/8/2026 Shop Release
Production Complete 10/15/2026 Production Complete
Order Close Out 10/19/2026 Order Close Out
Project Wrap Up 11/6/2026 Project Wrap Up
Lessons Learned Lessons Learned