Initial Quote Receipt & Review 10/6/2025 10/17/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 10/6/2025 10/17/2025 Final Quote Review Frank Edwards
Contract Review 10/13/2025 10/17/2025 Contract Review Frank Edwards
Order Entry 10/14/2025 10/17/2025 Order Entry Frank Edwards
Eng KickOff 10/15/2025 11/4/2025 Eng Kick Off Dylan Smith
Financial Review 11/3/2025 11/12/2025 Financial Review Frank Edwards
Initial Design Review Initial Design Review
Long Lead Release 10/13/2025 10/13/2025 Long Lead Release Date
Drawing Package Submittal 10/24/2025 11/6/2025 Drawing Package Submittal Date
Drawing Package Approval 10/31/2025 10/13/2025 Drawing Package Approval Date
Full BOM Release 11/5/2025 10/13/2025 Full BOM Release Date
Final Design Review 11/3/2025 Final Design Review
Design Completion Date 10/24/2025 Design Completion Date
Shop Release 2/9/2026 Shop Release
Production Complete 2/25/2026 Production Complete
Order Close Out 3/2/2026 Order Close Out
Project Wrap Up 3/6/2026 Project Wrap Up
Lessons Learned 3/27/2026 Lessons Learned