Milestone Map: QuoteNo: Q12587 / ProdNo: 1115616
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
10/6/2025
10/17/2025
Initial Quote Receipt & Review
Frank Edwards
Final Quote Review
10/6/2025
10/17/2025
Final Quote Review
Frank Edwards
Contract Review
10/13/2025
10/17/2025
Contract Review
Frank Edwards
Order Entry
10/14/2025
10/17/2025
Order Entry
Frank Edwards
Eng KickOff
10/15/2025
11/4/2025
Eng Kick Off
Dylan Smith
Financial Review
11/3/2025
11/12/2025
Financial Review
Frank Edwards
Initial Design Review
Initial Design Review
Long Lead Release
10/13/2025
10/13/2025
Long Lead Release Date
Drawing Package Submittal
10/24/2025
11/6/2025
Drawing Package Submittal Date
Drawing Package Approval
10/31/2025
10/13/2025
Drawing Package Approval Date
Full BOM Release
11/5/2025
10/13/2025
Full BOM Release Date
Final Design Review
11/3/2025
Final Design Review
Design Completion Date
10/24/2025
Design Completion Date
Shop Release
2/9/2026
Shop Release
Production Complete
2/25/2026
Production Complete
Order Close Out
3/2/2026
Order Close Out
Project Wrap Up
3/6/2026
Project Wrap Up
Lessons Learned
3/27/2026
Lessons Learned