Milestone Map: QuoteNo: Q12604 / ProdNo: 1116242
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
10/17/2025
10/17/2025
Initial Quote Receipt & Review
Derrick Herr
Final Quote Review
10/20/2025
10/24/2025
Final Quote Review
Frank Edwards
Contract Review
11/5/2025
Contract Review
Frank Edwards
Order Entry
11/6/2025
11/5/2025
Order Entry
Frank Edwards
Eng KickOff
11/10/2025
11/10/2025
Eng Kick Off
Paul Brown
Financial Review
11/12/2025
Financial Review
Initial Design Review
11/12/2025
Initial Design Review
Long Lead Release
11/13/2025
Long Lead Release Date
Drawing Package Submittal
11/14/2025
Drawing Package Submittal Date
Drawing Package Approval
11/21/2025
Drawing Package Approval Date
Full BOM Release
12/1/2025
Full BOM Release Date
Final Design Review
12/3/2025
Final Design Review
Design Completion Date
12/5/2025
Design Completion Date
Shop Release
1/12/2026
Shop Release
Production Complete
2/17/2026
Production Complete
Order Close Out
2/25/2026
Order Close Out
Project Wrap Up
2/27/2026
Project Wrap Up
Lessons Learned
Lessons Learned