Milestone Map: QuoteNo: Q12604 / ProdNo: 1116242


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 10/17/2025 10/17/2025 Initial Quote Receipt & Review Derrick Herr
Final Quote Review 10/20/2025 10/24/2025 Final Quote Review Frank Edwards
Contract Review 11/5/2025 Contract Review Frank Edwards
Order Entry 11/6/2025 11/5/2025 Order Entry Frank Edwards
Eng KickOff 11/10/2025 11/10/2025 Eng Kick Off Paul Brown
Financial Review 11/12/2025 Financial Review
Initial Design Review 11/12/2025 Initial Design Review
Long Lead Release 11/13/2025 Long Lead Release Date
Drawing Package Submittal 11/14/2025 Drawing Package Submittal Date
Drawing Package Approval 11/21/2025 Drawing Package Approval Date
Full BOM Release 12/1/2025 Full BOM Release Date
Final Design Review 12/3/2025 Final Design Review
Design Completion Date 12/5/2025 Design Completion Date
Shop Release 1/12/2026 Shop Release
Production Complete 2/17/2026 Production Complete
Order Close Out 2/25/2026 Order Close Out
Project Wrap Up 2/27/2026 Project Wrap Up
Lessons Learned Lessons Learned